Data centers in Wake County, North Carolina: 3 projects mapped
Wake County has turned away the data centers proposed for it so far, and most of its towns have stopped taking new ones. The largest was the New Hill Digital Campus, a 250-megawatt data center Natelli Holdings planned off Old U.S. Highway One in Apex, near Duke Energy's Shearon Harris nuclear plant and the Western Lake water reclamation plant. The Protect Wake County Coalition fought it over noise, air pollution and its use of energy and water, and in March 2026 Natelli withdrew its annexation and rezoning applications while the town worked on data center rules, saying the project could be revisited if Apex later allows them. "This isn't the end of the conversation," the coalition said.
Apex's council then voted unanimously in April for a one-year moratorium. "It's a big win," said Michelle Hoffner O'Connor of Protect Wake County. Holly Springs approved its own one-year pause in June, and by then Wake County itself, along with neighboring Chatham and Orange counties, had each put a one-year pause on new data centers in place.
In August the fight reached Raleigh. A developer asked the City Council to annex a nearly 14-acre site at 3101 Jones Sausage Road in the southeast of the city, near the Parrish Manor neighborhood and about 1,000 feet from the back of the Chelmshire Downs subdivision, for a 100,000-square-foot data center. Council member Mitchell Silver said hundreds of emails came in over a weekend, "the vast majority" opposed, and more than 30 residents signed up to speak. Mayor Janet Cowell said Beacon Partners, which had requested the annexation, withdrew the proposal that Saturday; Raleigh itself has not adopted a moratorium of its own.
Data center projects on record in Wake County
Grouped by the town each site sits in. The report above may name projects that have no record here yet.
Raleigh2
| Project | Company | Status | Power | |
|---|---|---|---|---|
| American Tower Edge Data CenterRaleigh | Not reported | Proposed | 4 MW | Source off site ↗ |
| Jones Sausage Road Data CenterRaleigh | Not reported | Cancelled | Not reported |
New Hill1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| New Hill Digital CampusNew Hill | Natelli Investments | Withdrawn | 250 MW |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Moratoriums and bans in effect
Pauses on new data centers covering this area.
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| Holly SpringsTown or city | Moratorium | Jun 17, 2026 | Jun 17, 2027 | Record off site ↗ |
| Wake County | Moratorium | Jun 2026 | Jun 2027 | Record off site ↗ |
| GarnerTown or city | Moratorium | May 19, 2026 | May 19, 2027 | Record off site ↗ |
| ApexTown or city | Moratorium | Apr 14, 2026 | Apr 14, 2027 | Record off site ↗ |
| WendellTown or city | Moratorium | Apr 14, 2026 | Dec 31, 2026 | Record off site ↗ |
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.