DeForest QTS Data Center, DeForest, Wisconsin

DeForest, WI 53532

QTS Data Centers·Blocked·650 acres·$12B·decided Feb 3, 2026

The siteImagery: Esri, Maxar

QTS Data Centers, of Virginia, wanted to build a $12 billion data center campus on about 650 acres in DeForest, Dane County, just north of Madison, Wisconsin, which would have required annexing roughly 1,600 acres from the neighboring town of Vienna. Village staff had been meeting with QTS and Alliant Energy since March 2025, seven months before the plan became public in October 2025, and the secrecy fed the backlash. On Tuesday, February 3, 2026, the DeForest Village Board voted 7-0 against the annexation, and QTS withdrew its rezoning and comprehensive-plan applications before the vote.

The pre-annexation deal DeForest had reached with QTS would have guaranteed at least $1.2 billion of taxable value for 15 years, worth an estimated $12 million a year to local governments by 2031 and $1,772 a year off the tax bill on a $400,000 home. It also included $100,000 a year for 15 years for the Yahara River, $200,000 a year for affordable housing, money toward a planned interstate interchange, and QTS paying for the water, sewer and road work the site needed. "It's our job to provide the best package that we can get from our development, to benefit the population and the village," village administrator Bill Chang said.

None of it was enough to keep the plan alive. "It has become clear that now is not the right time for our proposed project to move forward in DeForest," QTS said in a statement, adding it was disappointed with the outcome. Opposition had built around a Facebook group, No Data Center in DeForest, which grew past 4,100 members. Researcher Tyler Byrnes of the nonpartisan Wisconsin Policy Forum said the deal's public benefits went further than most: "You're not seeing these in other development agreements."

The DeForest Village Board, which turned this annexation down, would decide on any future data center proposal there. Several other Dane County communities, including Cottage Grove, Middleton, Westport and Dane County itself, have since adopted their own moratoriums while they write data center rules.

The facts on file

Company
QTS Data Centers
Address
DeForest, WI 53532
County
Dane County, Wisconsin
Country
United States
Status
Blocked
Land
650 acres
Reported size
650 acres, 5 buildings
Reported investment
$12B
Site
5396 Hahn Rd area, 1,600 acres to be annexed from Vienna

Sources

Everything above comes from these. Open one and check it yourself.

Moratoriums covering this site

PlaceTypeStartedEnds
Dane County Moratorium Jun 4, 2026 Dec 4, 2027 Record off site ↗

Share this

XFacebookText message

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.