Vantage describes a planned data center campus in Profile Park, Dublin. Its first two phases would provide two buildings with a combined 52 MW of critical IT load across 405,000 square feet. The company says the site has room for a third building.
The proposal includes an on-site 100 MVA generation plant designed to use hydrotreated vegetable oil and gas. Two separate Dublin data center planning appeals shown in the local wins table were refused: an application by Vantage Data Centres DUB11 in April 2025 and one by Digital Netherlands VIII for two buildings in February 2024. The cited records do not establish that either refusal is a decision on the Vantage campus described above.
Projects not tied to an area
Sites whose records name no county. Everything else is on the pages listed above.
Dublin1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Vantage DublinProfile ParkExact site not confirmed | Vantage Data Centers | Not reported | 52 MW | Source off site ↗ |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Where people here have won
Projects stopped by a vote, pulled by their developer, or blocked in court.
| Place | What happened | Date | Size | |
|---|---|---|---|---|
| ClondalkinVantage Data Centres | Denied by a vote National planning appeals board refused permission. | Apr 4, 2025 | Not reported | Story off site ↗ |
| Profile Park, ClondalkinDigital Netherlands VIII B.V. | Denied by a vote National planning appeals board refused permission for two data centers. | Feb 14, 2024 | Not reported | Story off site ↗ |
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.