Global Data Centers.formerly Florida Data Centers

Home/United States/Connecticut

Data centers by place

Data centers in Connecticut: 5 projects mapped

5 projects tracked
·
2 proposed or being built
·
1 operating
·
2 stopped or paused
·
20 MW from the 2 active projects that report a figure
·
3 moratoriums and bans in effect
GotSpace Data Center (Blocked)NE Edge Millstone (Waterford) (Cancelled, 300 MW)CyrusOne Norwalk NYM5 (Operating, 16 MW)Bristol Technology Center (Proposed, 4 MW)Atlas Capital Group Bloomfield concept (132 Griffin Road North) (Proposed)
Imagery: Esri, Maxar
Tracked projectStopped or pausedBigger dot, more power5 sites shown

The one data center moving forward in Connecticut is small. ReNew Developers wants a 15,000-square-foot building on Riverside Avenue in Bristol, on the former Dodge Village site beside the Pequabuck River, powered by a 4-megawatt fuel cell on site. The state Siting Council approved the fuel cell in December 2022, and Bristol's Inland Wetlands Commission approved the project in April 2026. Mayor Ellen Zoppo-Sassu wrote that it would buy city water and use closed-loop cooling, using about 30% of the water of a local grocery store.

The state's largest proposal is gone. NE Edge had planned a campus in Waterford drawing power directly from the Millstone Nuclear Power Station; in April 2026 its host fee agreement with the town ended in default, after nearly three years of opposition from the Concerned Citizens of Waterford and East Lyme. The group used grid operator data showing both Millstone reactors were offline for five weeks to challenge NE Edge's claim that it would not need backup generators.

Read more

Towns are acting before projects arrive. Groton adopted a one-year moratorium in 2022 and then zoning that bans data centers over 12,500 square feet, and Morris approved a two-year moratorium in 2026 to protect its farmland. "We can't control that, that's all state jurisdiction. This is something we can control," Morris zoning officer Tony Adili said. New Haven's draft ordinance lists West Haven among the towns that have paused or studied data centers.

In New Haven, Board of Alders Majority Leader Richard Furlow proposed a 12-month moratorium in July; it needs a committee public hearing before a final vote by the full board. The 2026 legislature ended without acting on bills to end the state's data center tax break or to regulate data centers drawing power from a plant such as Millstone.

3 counties with tracked projects

Only places with at least one project have a page.

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Where people here have won

Projects stopped by a vote, pulled by their developer, or blocked in court.

PlaceWhat happenedDateSize
WaterfordNE Edge Withdrawn by the developer After a three year campaign the host fee agreement between NE Edge-Waterford and the town ended in default and expired under its own terms. Apr 15, 2026 about 55 acres, 300 MW

Moratoriums and bans in effect

Places in Connecticut that have paused or banned new data centers.

PlaceTypeStartedEnds
West HavenTown or city Moratorium Jun 10, 2026 Jun 10, 2027 Record off site ↗
MorrisTown or city Moratorium May 26, 2026 May 26, 2028 Record off site ↗
GrotonTown or city Ban Jun 29, 2023 No end date Record off site ↗

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.