AirTrunk broke ground on its OSK1 data center in western Osaka, Japan, in February 2024. The company lists more than 20 MW of total capacity and about 16,500 square meters of gross floor area for OSK1.
DCD reported that the building would include 5,400 square meters of technical space and an on-site substation. The cited articles do not confirm an opening or the exact Amagasaki street address in the record.
The facts on file
- Company
- AirTrunk (Blackstone)
- Address
- 1-2-3 Nagasunishidori, Amagasaki, Hyogo 660-0807, Japan
- Region
- Hyogo
- Country
- Japan
- Status
- Under construction
- Power
- 20 MW
- Site location
- Exact parcel not confirmed, so the pin is approximate.
- Record checked
- Sep 17, 2026
Sources
Everything above comes from these. Open one and check it yourself.
Other projects nearby
Sites we track within 40 km.
- Vantage KIX1 (Osaka)listed on the Osaka page8 km
- Google Osaka8 km
- Equinix Osaka Saito Connected Campus (OS1/OS2/OS3)listed on the Osaka page8 km
- CloudHQ Osaka (KIX Cosmosquare)10 km
- NTT Osaka North 1 (OSK12 Ibaraki)16 km
- MC Digital Realty Osaka Saito (KIX/KIX11)16 km
- CyrusOne Osaka OSK1listed on the Kyoto page30 km
- NTT Keihanna (OSK11)listed on the Kyoto page30 km
Share this