Kasi Cloud (NSIA-backed) project

Kasi Cloud LOS1 data center, Lekki, Lagos

Lagos-Calabar Coastal Rd, Maiyegun, Lekki, Lagos, Nigeria

Kasi Cloud (NSIA-backed)·Operating·100 MW·announced 2022

The siteImagery: Esri, Maxar

Kasi Cloud Datacenters opened LOS1, the first building of its planned 100 megawatt data center campus, in the Maiyegun area of Lekki, Lagos State, Nigeria, in May 2026. Lagos Governor Babajide Sanwo-Olu, who presided over the 2022 groundbreaking, returned to officiate the flag-off ceremony, which Kasi described as LOS1's move from construction into operational readiness. The campus covers about four hectares next to six subsea internet cables, including Equiano and 2Africa.

Kasi broke ground in April 2022, when the project was reported to be backed by $250 million of investment, and the Nigeria Sovereign Investment Authority, which manages the country's sovereign wealth funds, is among its investors. Kasi has said the facility will be powered by gas, solar and battery storage, aiming for a power usage effectiveness rating (a measure of energy efficiency) below 1.6.

"For too long, Africa's data has powered someone else's economy. Today, that changes," said Johnson Agogbua, Kasi's founder and CEO. Kasi pitches the site as an in-country option under Nigeria's National Cloud Policy 2025, which it says requires sensitive government and financial data to be hosted in Nigeria. Finance Minister Taiwo Oyedele and NSIA chief executive Aminu Umar-Sadiq also attended the ceremony.

Most of Nigeria's data centers are clustered around Lagos, where Equinix, Digital Realty, MTN and Rack Centre also operate, and Kasi is developing another data center in Eket in southern Nigeria.

The rest of the campus is to be built out toward about 100 megawatts of IT capacity, and LOS1 now goes through phased commissioning, systems integration and customer readiness work before full commercial operations.

The facts on file

Company
Kasi Cloud (NSIA-backed)
Tenant
AI workloads
Address
Lagos-Calabar Coastal Rd, Maiyegun, Lekki, Lagos, Nigeria
Region
Lagos
Country
Nigeria
Status
Operating
Power
100 MW
On that figure
as reported in source; announced/planned unless status is operating
Announced
2022
Operating or planned
2026
Record checked
Sep 16, 2026

Sources

Everything above comes from these. Open one and check it yourself.

Other projects nearby

Sites we track within 40 km.

Share this

XFacebookText message

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.