Reeves County Solar Data Ranch data center, Reeves County, Texas

Reeves County, Texas, United States

LandBridge / NRG Energy·Proposed·1,100 MW

Area view. The exact parcel has not been made public.Imagery: Esri, Maxar

Nothing has been built at the Reeves County site in the Permian Basin of West Texas that trackers list as a solar data ranch, and there is no solar in the plan. In September 2025 NRG Energy and the landowner LandBridge agreed to explore a 1.1 gigawatt natural gas power plant beside the Waha gas hub, which NRG would build only if it first signs a long-term contract to sell the power to a data center operator.

Air permit applications and grid connection requests have been filed, and the companies say it could begin operating at the end of 2029 if a customer is found. LandBridge, formed by the private equity firm Five Point Infrastructure, holds about 277,000 surface acres across Texas and New Mexico.

The facts on file

Company
LandBridge / NRG Energy
Address
Reeves County, Texas, United States
County
Reeves County, Texas
Country
United States
Status
Proposed
Power
1,100 MW
On that figure
planned NRG gas-fired power plant to serve the potential data center, not IT load
Site location
Exact parcel not confirmed, so the pin is approximate.
Record checked
Sep 29, 2026

Sources

Everything above comes from these. Open one and check it yourself.

Other projects nearby

Sites we track within 40 km.

Moratoriums covering this site

PlaceTypeStartedEnds
TexasState Moratorium Aug 3, 2026 No end date Record off site ↗