OpenAI Stargate Milam (Under construction, 1,200 MW) Microsoft Project Kilby (Proposed, 2,000 MW) Lancium Clean Campus (Under construction, 1,200 MW) Reeves County Solar Data Ranch (Proposed, 1,100 MW) AWS GW Ranch (Pecos County) (Under construction, 7,650 MW) Tract Caldwell Valley (Uhland) (Proposed, 4,000 MW) PowerHouse Grand Prairie (Midlothian) (Proposed, 1,800 MW) CoreWeave Project Horizon (West Texas) (Under construction, 2,000 MW) Frontier Vantage Data Center (Under construction, 1,400 MW) Fermi America HyperGrid/ Project Matador (Under construction, 17,000 MW) PowerBridge/LandBridge (Proposed, 2,000 MW) Lancium Childress (Proposed, 1,000 MW) Meta Project Seafox (Under construction, 1,000 MW) Fort Bliss Data Center (Proposed, 3,000 MW) Eneus Energy (Proposed, 2,000 MW) Lacy Lakeview Data Center (Proposed, 1,000 MW) BaRupOn Data Center (Under construction, 3,000 MW) Project Lufkin: Amp Z Data Center (Proposed, 2,100 MW) Kahla Project (Proposed, 1,500 MW) CloudBurst Data Center (Approved, 1,200 MW) Sulphur Springs Matrix Data Center Campus (Proposed, 3,000 MW) IREN Sweetwater Hub (Under construction, 2,000 MW) Crusoe/Blue Energy Data Center (Proposed, 1,500 MW) Crusoe Abilene Expansion (Under construction, 900 MW) CyrusOne Freestone County TX (Under construction, 760 MW) Aligned Project Caprock (Abernathy) (Under construction, 540 MW) CloudHQ San Antonio (SAT) (Proposed, 600 MW) Tract Applewhite (Poteet) (Proposed, 720 MW) Tract Medina Technology Park (Proposed, 500 MW) Cipher Mikeska (Doole) (Proposed, 500 MW) Cipher Milsing (Proposed, 500 MW) Cipher McLennan (Riesel) (Proposed, 500 MW) Hut 8 Beacon Point (Corpus Christi) (Under construction, 704 MW) CleanSpark Data Center (Proposed, 600 MW) Childress Data Center (Operating, expanding, 750 MW) Nexus Data Center: Apex DFW HB1 and HB2 (Under construction, 600 MW) Skybox Hutto PowerCampus Data Center (Under construction, 600 MW) Bitdeer AI (Operating, expanding, 563 MW) Riot Platforms Rockdale Data Center Campus (Operating, expanding, 700 MW) Emergent Data Center (Proposed, 600 MW) OpenAI Stargate Abilene (Operating, expanding, 300 MW) CoreWeave Denton TX (Operating, 262 MW) Meta Temple (Operating, 152 MW) CoreWeave Helios (Operating, 200 MW) Google Midlothian (Operating, 103 MW) Anthropic Barber Lake (Under construction, 300 MW) Compass Red Oak Roadrunner (Austin Blvd) (Operating, 360 MW) Streams San Antonio III (Under construction, 200 MW) AWS Project Spectrum (Hood County) (Withdrawn) Core Scientific Pecos (Cottonwood) (Operating, 300 MW) Cipher Mining Black Pearl (Operating, expanding, 300 MW) TeraWulf Abernathy (Fluidstack) (Under construction, 168 MW) CyrusOne Whitney (Bosque County) (Under construction, 400 MW) CyrusOne Fort Worth (DFW7) (Under construction, 200 MW) CyrusOne Jack County TX (Proposed, 144 MW) QTS Irving (Operating, 165 MW) STACK Dallas (DFW02 Belt Line) (Not reported, 460 MW) Digital Realty Digital Dallas (Richardson) (Operating, 100 MW) T5 AllianceTexas (Fort Worth) (Proposed, 400 MW) NTT Garland Campus (TX1-TX4) (Operating, 124 MW) Prime Austin (AUS01 Uhland) (Proposed, 384 MW) PowerHouse Irving (Las Colinas) (Under construction, 201 MW) Stream San Antonio (SATA Military Dr) (Under construction, 200 MW) Stream Wilmer (DFWC) (Proposed, 240 MW) DataBank Red Oak Campus (DFW9-DFW16) (Under construction, 480 MW) Marathon Digital Garden City (ex-Applied Digital) (Operating, 200 MW) Core Scientific Hunt County (Wieland) (Proposed, 285 MW) Cipher Odessa (Operating, 207 MW) Cipher Stingray (Andrews) (Proposed, 100 MW) Cipher Ulysses (Proposed, 200 MW) CleanSpark Sealy Data Center (Proposed, 285 MW) Project Gladys (Soluna) (Proposed, 150 MW) Brownsville Data Center (Withdrawn) Project Aggie (Blocked, 600 MW) Riot Platforms (Operating, expanding, 400 MW) Texas Critical Data Centers (Approved, 250 MW) Project Horizon (Proposed, 400 MW) Lone Star Project (Proposed, 100 MW) Serverfarm Data Center (CTX 1, CTX 2) (Operating, expanding, 100 MW) Project Hutto (Withdrawn, 70 MW) Mesone Data Center (Proposed, 200 MW) ONMINE Data Center (Withdrawn) Texas Solarworks LLC (Withdrawn) Data Center THM1A (Under construction, 440 MW) North East Data Center LLC (Under construction, 300 MW) FO Permian Partners and HiVolt Energy Data Center (Proposed, 150 MW) Project Fei (Proposed, 240 MW) Project Hedy (Proposed, 198 MW) Project Ellen (Proposed, 145 MW) Project Rosa (Proposed, 242 MW) Project Big Pine (Proposed, 300 MW) APR Energy Data Center (Proposed, 400 MW) Skybox Atlantic Station (Proposed, 100 MW) Pyote Data Center (Operating, 195 MW) San Marcos Data Center (Blocked, 380 MW) Project Kati 1 and 2 (Under construction, 166 MW) Flexential Data Center (Proposed, 108 MW) Project Comal (Approved, 360 MW) Rowan AUS01 (Under construction, 300 MW) Diode Ventures Data Center (Withdrawn) Vulcan Core bitcoin mining facility (Tyler) (Blocked, 12 MW) Hut 8 Vega (Operating, 205 MW) Microsoft SAT40 (Operating, 75 MW) CyrusOne Allen (Operating, 77 MW) STACK DFW01 (Plano) (Operating, 80 MW) CyrusOne Houston HOU3-HOU4 (Operating, 84 MW) QTS Fort Worth (Operating, 70 MW) QTS San Antonio (Operating, 90 MW) Sabey Round Rock (Operating, 84 MW) Cipher Reveille (Cotulla) (Proposed, 70 MW) Legacy Data Center (Approved, 50 MW) Galaxy Digital Project Merlin (McGregor) (Approved, 75 MW) Project Annie (Proposed, 74 MW) Project Dorothy 1A and 1B (Operating, 50 MW) Rowdy Data Center (Operating, 70 MW) Microsoft SAT14 (Operating, 47 MW) Vantage TX1 (Under construction, 32 MW) Core Scientific Austin (Operating, 20 MW) CoreWeave Plano (Operating, 30 MW) CyrusOne San Antonio (Omicron) (Operating, 33 MW) CyrusOne San Antonio (Westover Hills) (Operating, 36 MW) CyrusOne Austin AUS2-AUS3 (Operating, 19 MW) CyrusOne Carrollton DFW1 (Operating, 45 MW) CyrusOne Lewisville DFW2 (Operating, 12 MW) Prime Dallas (DFW01 Round Table) (Operating, 20 MW) Stream DFW VII (Garland) (Operating, 43 MW) Stream Houston (The Woodlands) (Operating, 7.8 MW) Alborz (WindHQ, ex-Cipher stake sold to Canaan) (Operating, 40 MW) Viridien Data Center (Proposed, 21 MW) Blueprint Project (Approved, 25 MW) Project Raptor (Approved, 40 MW) HyperDataGrid Data Center (Under construction, 20 MW) Matagorda County Data Centers (Proposed, 20 MW) Chase Tower McAllen Data Center (Operating, 1.5 MW) Project Dorothy 2 (Operating, 48 MW) Oppidan Data Center (Proposed, 5 MW) Blueprint Projects (Under construction, 30 MW) Google Red Oak (Operating) Goodnight (Under construction) Meta Fort Worth (Operating) Aligned Plano Campus (DFW-01/02) (Operating) Lambda Plano (Aligned DFW-04) (Under construction) Aligned DFW-01 / DFW-03 (Under construction) Compass Red Oak (Approved) Black Mountain Power Fort Worth (Approved) Rock Creek Data Center Campus (Approved) Microsoft Medina County (SAT93) (Under construction) AWS Bastrop County (Cedar Creek) (Not reported) AWS Project Eagle (Boling) (Under construction) AWS Horizon Junction (Floydada) (Under construction) AWS San Antonio Bitter Blue (Proposed) CyrusOne Medina County TX (Not reported) CyrusOne Sulphur Springs TX (Proposed) QTS Hall County Texas (Proposed) QTS South Dallas (Wilmer) (Under construction) Compass Allen (Not reported) Digital Realty DFW10 (2323 Bryan St) (Operating) Digital Realty Houston (Meadows Place) (Operating) Digital Realty Garland (Not reported) Digital Realty Austin (7620 Metro) (Operating) Equinix Dallas Infomart Interconnection Hub (DA1-DA4, DA6) (Operating) Equinix Dallas Suburban Campus (Plano DA9/DA11) (Operating) Equinix Houston Hub (HO1) (Operating) Switch The Rock (Round Rock) (Approved) Switch Round Rock East (Louis Henna Blvd) (Not reported) Switch Smith School Rd (Austin) (Operating) Lambda Austin (Met Center) (Not reported) Switch Houston 2/3 (Greenspoint) (Operating) T5 Dallas Campus (Plano) (Operating) Prime Fort Worth (Benbrook DFW04) (Not reported) Prime Garland (Not reported) PowerHouse Circle T (Westlake) (Proposed) PowerHouse Red Oak (Not reported) PowerHouse Caldwell County (Uhland) (Not reported) Stream Project Saltworks (Graham, former Plug Power hydrogen site) (Proposed) Stream San Antonio II (SATB Westover Hills) (Under construction) Stream DFW III (Plano Legacy) (Operating) DataBank Dallas metro (DFW1-DFW8) (Operating) Cipher Apollo (San Antonio option) (Proposed, early stage) Lambda Houston (ECL TerraSite Sugar Land) (Proposed) Fluidstack Cameron County (Harlingen) (Under construction) Giga Texas Datacenter (Operating) EdgeConneX AUS02 (Under construction) Fort Hood Data Center (Proposed) Cawley Partners (Proposed) Georgetown Data Center (Operating) MARA Bitcoin Mining Data Center (Operating) Journey 1A and 2A Data Centers (Under construction) Provident Data Center (Proposed) Iron Mountain Data Center (Proposed) Experian McKinney Data Center (Operating) Project Pumpkin 2A (Under construction) Project Rise 1A and Project Rise 2A (Under construction) Cornerstone Southwest Data Center (Operating) BT Gateway Data Center (Proposed) Texarkana Data center (Operating) Comanche Circle Data Centers (Approved) Black Mountain Power Data Center (Proposed) Venus Data Center (Proposed) Willis Data Center (Operating) Palomino Alpha Data Center (Proposed) Imagery: Esri, Maxar
Texas has halted state approvals for new data centers. On September 21 Gov. Greg Abbott ordered the Texas Commission on Environmental Quality to issue no permits for data center projects until state audits of their power and water use are done, widening the freeze on new grid connections he ordered August 3. "Simply put, Texans must come first," Abbott wrote. The biggest projects under construction include Fermi America's HyperGrid in Carson County, IREN's campus at Sweetwater and SB Energy's sites in Milam County.
The audits ask developers for their electricity and water use, tax breaks, ownership and plans to limit harm to neighbors. Only about 28% of data centers answered a state water-use survey, and on September 14 Abbott told the Texas Water Development Board to penalize those that do not report. Counties have little power of their own: Hood County dropped a moratorium after state Sen. Paul Bettencourt said it had no legal authority, and Hill County rescinded one after a developer sued for $100 million.
Cities are acting too. San Marcos became the first Texas city to ban data centers, voting 4-3 on June 16 to make them ineligible anywhere in the city; Bettencourt says he will challenge the ban. Fort Worth's council voted unanimously in August to start a 90-day moratorium, which under state law needs public hearings first. The first hearing is set for November 10, and the pause would begin February 16, 2027.
Send a letter to your county commissioners in Texas There are 117 data center projects in Texas proposed or under construction right now and four local pauses on new data centers are already in force here. A letter from a resident is a public record they have to answer.
13,864 letters sent so far.
Write my letter Takes about 60 seconds. It goes to every official on the record for your address within 24 hours.
82 counties with tracked projects Only places with at least one project have a page.
Where this comes from The reporting above was written from these. Open one and check it yourself.
Where people here have won Projects stopped by a vote, pulled by their developer, or blocked in court.
Place What happened Date Size
Brownsville Randr Ventures
Withdrawn by the developer The applicant withdrew the day before the city met to consider a 90 day moratorium on new data centers.
Aug 5, 2026
Not reported
Henderson County (Cedar Creek Lake) Diode Ventures
Withdrawn by the developer Diode pulled out after residents fought its plan to draw lake water, and Gov. Abbott said it failed the state's new standards.
Jul 23, 2026
Not reported
Tyler Vulcan Core LLC
Denied by a vote The planning and zoning commission refused the special use permit 5-2 after 26 residents spoke against it and the meeting ran three and a half hours.
Jul 7, 2026
1.8 acres, 12 MW
Killeen Onmine
Withdrawn by the developer Planning and Zoning recommended denial 4-1 on April 27, then the applicant withdrew before the June 2 council vote.
May 2026
2.6 acres
Hutto Zydeco Development
Withdrawn by the developer Zydeco withdrew its rezoning after city staff recommended denial and neighbors filed formal protests.
Apr 17, 2026
70 MW, 40 acres
San MarcosHighlander SM One LLC
Denied by a vote City Council voted 5-2 to deny the rezoning; the city later banned data centers in every zone (June 16).
Mar 2026
200 acres
Story off site ↗
College Station Priority Power (Project Aggie)
Denied by a vote City Council voted unanimously against selling the land after a 5,000-signature petition and nearly 80 speakers.
Sep 11, 2025
200 acres, up to 600 MW
Moratoriums and bans in effect Places in Texas that have paused or banned new data centers.
Zoning limits on data centers Rules short of a pause: setbacks, noise caps, permit requirements and district limits.