Soluna project

Project Dorothy 1A and 1B data center, Silverton, Texas

9985 Co Rd F, Silverton, TX 79257

Soluna·Operating·50 MW

The siteImagery: Esri, Maxar

Soluna's data center campus just south of Silverton, off Highway 207 in Briscoe County, Texas, runs on the wind: the company says it has built 98 megawatts of what it calls renewable computing there. The first two buildings, Dorothy 1A and 1B, have a combined 50 megawatts and are used for bitcoin hosting and mining.

In April 2026 Soluna bought the 150 megawatt Briscoe Wind Farm that feeds the site for $53 million, then paid $16.5 million for Spring Lane Capital's stake in Dorothy 1A to own it outright. "With Briscoe secured and Dorothy 1A now fully owned, we have the foundation for what comes next: a vertically integrated AI campus, from energy generation to compute infrastructure, that we control end to end," chief executive John Belizaire said. The company says the campus will move from bitcoin mining to AI as its main workload over the medium term.

"We've had for a couple of years a bitcoin mining facility, and it's filled in a gap of when we lost our abatement, our pilot money from the wind farms," County Judge Rank Cogdell told KVII in July 2026. With a larger data center planned, the county is weighing a tax abatement as a way to put safeguards in place, and commissioners were working with the company on a town hall where residents could ask questions. "It might even create more income for other businesses to come in, and of course our town is struggling; the whole county is struggling at this time," said Danny Francis, the Precinct 3 commissioner. That next phase, Dorothy 3, is an AI campus of up to 300 megawatts on 397 acres Soluna bought beside the existing buildings, across from the wind farm's substation.

The facts on file

Company
Soluna
Address
9985 Co Rd F, Silverton, TX 79257
County
Briscoe County, Texas
Country
United States
Status
Operating
Power
50 MW

Sources

Everything above comes from these. Open one and check it yourself.

Other projects nearby

Sites we track within 40 km.

Moratoriums covering this site

PlaceTypeStartedEnds
TexasState Moratorium Aug 3, 2026 No end date Record off site ↗

Share this

XFacebookText message

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.