Global Data Centers.formerly Florida Data Centers

Home/Companies/Soluna

Data centers by company

Soluna data centers: 8 sites mapped

8 projects tracked
·
5 proposed or being built
·
3 operating
·
932 MW across all 8 active projects
·
1 country
Project Gladys (Soluna) (Proposed, 150 MW)Project Hedy (Proposed, 198 MW)Project Ellen (Proposed, 145 MW)Project Rosa (Proposed, 242 MW)Project Annie (Proposed, 74 MW)Project Dorothy 1A and 1B (Operating, 50 MW)Project Sophie (Operating, 25 MW)Project Dorothy 2 (Operating, 48 MW)
Boundaries: Natural Earth
Tracked projectBigger dot, more power8 sites shown

Soluna Holdings, based in Albany, New York, builds data centers for bitcoin mining and increasingly for AI beside wind, solar and hydroelectric plants, using power that would otherwise go to waste. As of August 1, 2026 it operated about 192 megawatts across three energized sites in Texas and Kentucky, with more under construction and a Texas pipeline it puts at about 6.3 gigawatts. In August 2026 it enlarged several projects for AI: Rosa grew from 187 to 242 megawatts, Hedy from 120 to 198, and Ellen, in Cameron County, from 100 to 145.

Its main campus is Dorothy, south of Silverton in Briscoe County, where two buildings run on the 150 megawatt Briscoe Wind Farm next door. Soluna bought the wind farm for $53 million in April 2026, then closed in August on 397 more acres for Dorothy 3, an AI campus of up to 300 megawatts. Briscoe County Judge Rank Cogdell said the site has "filled in a gap" left when the county lost tax abatement money from the wind farms, and commissioners are weighing an abatement for the larger plan.

In the Rio Grande Valley, Willacy County welcomes Project Kati for its taxable value, but neighboring Cameron County has said it will not offer data centers tax abatements and had received no permit applications as of May 2026. Since August 3, 2026, new data center connections to the Texas grid have been on hold while state regulators audit projects in the queue. In Kentucky, Calloway County's fiscal court took up a 12-month data center moratorium in July 2026 that would block any expansion of Soluna's existing bitcoin mine in Murray.

Soluna sites on record

Grouped by country, then by state or region, biggest first. Open one to see the projects there. The report above may name sites that have no record here yet.

United States8 · 932 MW
Texas7
ProjectCompanyStatusPower
Project Rosanear Santa RosaExact site not confirmed Soluna Proposed 242 MW
Project Hedynear LyfordExact site not confirmed Soluna Proposed 198 MW
Project Gladys (Soluna)southeast Texas (site not disclosed by Soluna)Exact site not confirmed Soluna Proposed 150 MW
Project Ellennear Rio HondoExact site not confirmed Soluna Proposed 145 MW
Project Annienortheast Texas (exact location undisclosed by Soluna)Exact site not confirmed Soluna Proposed 74 MW
Project Dorothy 1A and 1BSilverton Soluna Operating 50 MW
Project Dorothy 2Silverton Soluna Operating 48 MW
Kentucky1
ProjectCompanyStatusPower
Project SophieMurrayExact site not confirmed Soluna Operating 25 MW

Every data center in United States

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.