CoreWeave Hammond data center, Hammond, Indiana
301 Digital Crossroads Dr, Hammond, IN 46320
Digital Crossroads·Suspended·180 MW
Hammond approved the largest economic development project in the city's history, and then watched the deadline pass. The city council approved the development agreement 8 to 0 in June 2025, for a data center at 301 Digital Crossroads Drive in Hammond, Lake County, Indiana, built to CoreWeave's specifications and expanding the company's existing presence at the campus.
On July 1, 2026 the city announced that the agreement had expired. It bound four parties: the City of Hammond, the Hammond Redevelopment Commission, Decennial Group and CoreWeave. Certain milestones and obligations had to be met by June 30, 2026. They were not, and two extensions had already been granted. The city said no further extension would be offered, and did not say which milestones were missed. Mayor Thomas M. McDermott Jr. said: "While we are disappointed that the project did not move forward under the terms of this agreement, we appreciate the time and effort invested by all parties throughout the process." The city said it will keep looking for development at the site, which it calls one of the premier locations for large scale economic development in the Midwest.
The facts on file
- Company
- Digital Crossroads
- Tenant
- CoreWeave
- Address
- 301 Digital Crossroads Dr, Hammond, IN 46320
- County
- Lake County, Indiana
- Country
- United States
- Status
- Suspended
- Power
- 180 MW
- On that figure
- planned facility size stated by CoreWeave at approval ("180-megawatt facility"); never built
- Record checked
- Sep 29, 2026
Sources
Everything above comes from these. Open one and check it yourself.
Other projects nearby
Sites we track within 40 km.
- Robbins Incinerator Data Center16 km
- Digital Realty ORD10 (350 E Cermak)listed on the Cook County page18 km
- Equinix Chicago Downtown Hub (CH1/CH2/CH4)listed on the Cook County page18 km
- QTS Chicago19 km
- 300 West Adams Data Center21 km
- Lambda Chicago (EdgeConneX Stickney)27 km
- AWS Hobart Indiana29 km
- PowerHouse Hobart (Indiana)29 km
Moratoriums covering this site
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| Lake County | Zoning limits | Aug 12, 2025 | No end date | Record off site ↗ |
Share this
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.