Global Data Centers.formerly Florida Data Centers

Home/United States/Georgia/Troup County

Data centers by place

Data centers in Troup County, Georgia: 3 projects mapped

3 projects tracked
·
2 proposed or being built
·
1 stopped or paused
·
1,000 MW across all 2 active projects
Hogansville Data Center (Proposed, 600 MW)Project Pegasus (Under construction, 400 MW)Project West (Blocked, 600 MW)
Imagery: Esri, Maxar
Tracked projectStopped or pausedBigger dot, more power3 sites shown

Google is building a data center at 411 Pegasus Parkway in LaGrange, confirmed in April 2026 as the company's second in Georgia. Google says it will cover the full cost of the site's power and infrastructure and is funding utility upgrades for at least 50 LaGrange families. A second, unbuilt project, Fertile Ground Investments' proposed 600-megawatt campus near Hogansville, is still working through a land purchase and rezoning.

The Hogansville project, run by Fayetteville developer Luis Matta, would sit on 437 acres the city agreed to sell for $12,000 an acre under a non-disclosure agreement officials kept for 18 months; residents learned of it only after an open records request. "It's infuriating," said Hogansville resident Paula Darden. The city has since refused to rezone land for it: on August 17, 2026 the council voted 4-1 against creating a heavy industrial district, then extended its moratorium to a September 8 meeting; no outcome from that meeting has been published.

Read more

LaGrange rejected a separate $9.7 billion, 600-megawatt proposal called Project West in March 2025 when the council would not annex the 513 acres it needed. The city now requires a special-use permit for any new data center; one is pending for a 134-acre site on Pegasus Parkway proposed by the developer Fairpoint, recommended for approval by planners in July with a public hearing that was due by September 22.

Troup County itself adopted a 17-page ordinance in 2026 requiring a special-use permit for every data center, confining them to heavy industrial zoning with a 1,500-foot setback and Tier 4 diesel generators; the Troup County Anti-Data Center Coalition said it did not go far enough.

Data center projects on record in Troup County

Grouped by the town each site sits in. The report above may name projects that have no record here yet.

LaGrange2
ProjectCompanyStatusPower
Project WestLaGrange Project West WHP - GA LLC Blocked 600 MW
Project PegasusLaGrange Google Under construction 400 MW
Hogansville1
ProjectCompanyStatusPower
Hogansville Data CenterHogansville Fertile Ground Investments LLC Proposed 600 MW

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.