SAMX Data Center, Remington, Virginia

11825 REMINGTON RD, Remington, VA 22734

SAMX Data·Proposed

The siteImagery: Esri, Maxar

SAMX Data LLC wants to rezone 55.26 acres at 11825 Remington Road, near Remington in Fauquier County, Virginia, for a data center campus of two three-story buildings, 300,000 to 350,000 square feet each. The application, filed in October 2023, has not been resubmitted since SAMX asked for more time in 2024; the county had no new submission as of August 2025. On September 17, 2026 the Fauquier County Planning Commission unanimously recommended removing data centers as a permitted use in the business park zoning district SAMX is requesting.

County staff raised concerns about the plan's consistency with its proffers, uncertain electrical service and its proposed use of groundwater, the Piedmont Environmental Council reported. Three other data center bids near Remington were withdrawn in the following weeks: Gigaland pulled its application a second time on August 17, a month after the Planning Commission voted 4-1 to recommend denial; Convergent VA withdrew its Convergent Technology Park in late August, saying it would build houses instead; and the Remington Innovation Campus applicants withdrew hours before a September 17 hearing.

The neighboring Remington Technology Park, rezoned in 2018 for up to six data centers, had also stalled over power supply; on July 10, 2026 supervisors approved its developer's plan to run the site on natural gas fuel cells rather than wait years for grid capacity. The commission's new recommendation would limit new data centers in Fauquier to land near Vint Hill and require every project to get a special exception from the Board of Supervisors, which decides both that zoning change and any SAMX rezoning.

The facts on file

Company
SAMX Data
Address
11825 REMINGTON RD, Remington, VA 22734
County
Fauquier County, Virginia
Country
United States
Status
Proposed

Sources

Everything above comes from these. Open one and check it yourself.

Other projects nearby

Sites we track within 40 km.

Moratoriums covering this site

PlaceTypeStartedEnds
Fauquier County Zoning limits Dec 14, 2023 No end date Record off site ↗

Share this

XFacebookText message

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.