STACK Stafford (Under construction, 1,100 MW) EdgeCore Data Center (Under construction, 1,100 MW) Dahlgren West (Approved, 1,200 MW) AWS Mattameade / Orrock Tech Campus (Under construction, 770 MW) Digital Realty Digital Loudoun (Ashburn) (Operating, 500 MW) Tract Goochland (Proposed, 900 MW) PowerHouse 95 (Spotsylvania) (Under construction, 900 MW) XX Tech Park (Proposed, 900 MW) CleanArc VA1 Data Center Campus (Under construction, 900 MW) QTS Richmond 1 (Operating, 238 MW) QTS Richmond 2 (Operating, 180 MW) QTS Richmond 3 (Operating, 240 MW) Google Bristow (Operating, 238 MW) STACK Infrastructure NVA02 (Operating, 420 MW) STACK Manassas (NVA05 Freedom Center) (Not reported, 150 MW) Prince William Digital Gateway (Withdrawn, 1,800 MW) AWS Lake Anna Tech Campus (Under construction, 420 MW) AWS Louisa County Third Campus (Withdrawn) Vantage VA1 (Ashburn I) (Operating, 206 MW) Vantage VA3 (Ashburn III) (Under construction, 288 MW) Vantage Fredericksburg (Under construction, 192 MW) CyrusOne Sterling NVA5-NVA7 (Operating, 116 MW) CloudHQ Manassas MCC Campus (Operating, 382 MW) CloudHQ Manassas MDC Campus (Proposed, 300 MW) EdgeCore Culpeper (Under construction, 196 MW) QTS Manassas 1 (Operating, 190 MW) STACK Loudoun County (Evergreen Mills) (Proposed, 180 MW) STACK Sterling (NVA04 Lockridge) (Not reported, 200 MW) CloudHQ Culpeper (CLP) (Proposed, 215 MW) NTT Gainesville Campus (VA10-VA13) (Proposed, 336 MW) Iron Mountain Richmond (White Oak Technology Park) (Proposed, 200 MW) PowerHouse Pacific (former AOL HQ) (Under construction, 265 MW) PowerHouse Arcola (Under construction, 120 MW) DataBank Culpeper Campus (Proposed, 192 MW) Mountain Road Technology Park (Tract) (Blocked, 900 MW) Sanders Lane Assemblage I LLC · Prince William County (Blocked) Project Hercules (Avaio Digital, Appomattox) (Proposed, 300 MW) LS Power (Withdrawn) Catlett Data Center Park (Cancelled) Diode Ventures Data Center (Withdrawn) Pittsylvania County Data Center (Blocked) Tract Data Center (Withdrawn) STACK Berry Hill (Danville) (Approved, 299 MW) Penzance Development Data Center (Blocked) Hunting Hawk Data Center (Cancelled, 900 MW) Province Group Powhatan Technology Park (Approved, 400 MW) Menlo Equities MD-VA3 Data Center (Proposed, 104 MW) NuVu Data Center (Approved, 300 MW) Convergent Technology Park (Withdrawn, 240 MW) Gigaland Remington Data Center (Withdrawn, 800 MW) Remington Innovation Campus (Withdrawn) Remington Technology Park (Approved, 300 MW) Wagner Urban Logistics LLC Data Center (Blocked) Crusoe Project Flash (Summit View Business Park) (Cancelled, 100 MW) Caroline Center for Innovation - North (Withdrawn) VALCO Data Center Park (Withdrawn) Google Botetourt County Data Center Campus (Approved, 300 MW) Project Tallmadge (Proposed, 320 MW) Google Arcola (Operating, 77 MW) CoreWeave Chester VA (Operating, 82 MW) QTS Ashburn (Broderick Drive) (Operating, 55 MW) Vantage VA2 (Ashburn II) (Operating, 96 MW) STACK Ashburn (NVA06 Compass Creek) (Not reported, 72 MW) Compass Loudoun County (Sycolin Rd) (Operating, 79 MW) Compass Loudoun County I (Thunderball Dr) (Operating, 79 MW) Aligned IAD-03 (Sterling) (Not reported, 72 MW) Sabey Intergate.Ashburn (Operating, 85 MW) T5 Westfields (Chantilly) (Proposed, 60 MW) PowerHouse ABX-1 Beaumeade (Ashburn) (Operating, 60 MW) DataBank Ashburn Campus (IAD1-IAD3) (Operating, 69.9 MW) QTS Ashburn-Moran (Operating, 4 MW) CyrusOne Sterling (Ridgetop) (Operating, 44 MW) CyrusOne Sterling NVA4 (Operating, 11 MW) CyrusOne Sterling NVA8 (Operating, 24 MW) CyrusOne Sterling NVA9 (Operating, 38 MW) STACK Ashburn (NVA01 Pacific Blvd) (Operating, 17 MW) Hopewell Data Center (Not reported, 20 MW) Middletown Data Center (Operating, 6 MW) EdgeConneX Norfolk (Operating, 0.75 MW) DC Blox Richmond (Azalea Flea Market site) (Proposed, 10 MW) ELIAS DC ASSETS (Operating, 3 MW) Mineral Gap Data Center (Operating, expanding, 45 MW) QTS Richmond 5 (Proposed) Google Project Loch (Chesterfield County) (Approved) Meta Henrico (Operating) Microsoft Leesburg (Operating) Oracle Ashburn (Operating) CyrusOne Shaw Road (Operating) Wilderness Crossing (Proposed) Starwood Plaza 500 (Proposed) Amazon Warrenton (Approved) Google Leesburg (Operating) Google Project Peanut (Chester) (Under construction) Microsoft Jacksonville Road (Manassas) (Under construction) Microsoft Boydton (Operating) Microsoft Hillcrest (Chesterfield) (Approved) Microsoft Growth Mindset (Sterling) (Under construction) AWS Northeast Creek Technology Campus (Under construction) AWS Desper Creek Technology Campus (Not reported) AWS Stevensburg (Culpeper) (Under construction) AWS Manassas Tanner Way (Operating) AWS Manassas Innovation Drive (Operating) AWS Manassas Vulcan Lane (Proposed) AWS Manassas Nokesville Road (Under construction) AWS Stafford Potomac Church (Under construction) AWS Cosner Tech Campus (Spotsylvania) (Under construction) AWS Carter's Store Tech Campus (Proposed) AWS Summit Crossing Tech Campus (Under construction) AWS Birchwood (King George) (Proposed) AWS Devlin Technology Park (Bristow) (Approved) AWS Bridgefield Tech Center (Ashburn) (Proposed) AWS Reeds Farm Lane (Dulles) (Under construction) AWS Pathfinder Plaza (Sterling) (Operating) AWS Renaissance Technology Park (Herndon) (Under construction) AWS Mallory Drive (Chantilly) (Operating) AWS Haymarket (Operating) CyrusOne Broadlands (Ashburn) (Approved) CloudHQ Manassas (MCC1/MCC2) (Operating) CloudHQ Ashburn (LC1) (Operating) CloudHQ Ashburn LC2 (Waxpool) (Not reported) CloudHQ Ashburn LC5 (Lockridge) (Not reported) Aligned Ashburn (IAD-01) (Operating) STACK Fredericksburg (Gordon Shelton) (Proposed) EdgeCore Ashburn Campus (AS01) (Under construction) Digital Realty ACC Campus (Ashburn) (Operating) Digital Realty Digital Dulles (Sterling) (Operating) Digital Realty VA3 (Manassas) (Operating) Digital Realty VA4 (Bristow) (Not reported) Equinix Ashburn Mega-Campus (DC1-DC15) (Operating) Equinix Culpeper High-Security Campus (CU1–CU4) (Operating) NTT Ashburn Campus (VA1-VA9) (Operating, expanding) Iron Mountain Virginia Campus (VA-1 to VA-9) (Operating, expanding) Tract Hanover County (Richmond) (Approved) PowerHouse Quantum Connect (Quantum Park) (Not reported) PowerHouse CTP Richmond (Digital Drive / CTP-02 / CTP-03) (Under construction) Lambda Ashburn (Red Rum Dr) (Operating) Bull Church Data Center (Proposed) Green Energy Ventures Data Center (Approved) Ladysmith Technology Park (Proposed) Ironhorse East Ashland (Proposed) Pixel Factory (Operating) Brush Mountain Blacksburg (Operating) OnePartner Duffield Data Center (ATAC) (Operating) Mid-Atlantic Advanced Manufacturing Center (Proposed) Data center (Proposed) Blaisdell Property Data Center (Proposed) Cranes Corner Data Center (Approved) Enon Road Technology Park (Proposed) Forest Lane Data Center (Proposed) Sisson North (Proposed) Cavalier Innsbrook Data Center (Operating) DBT Data Cyber Integration Center (Operating) Spring Valley Technology Park (Proposed) Tuscarora Crossing Landbay 3 (Proposed) Cabin Field Road Data Center (Proposed) Mid-County Industrial Park (Approved) PARSONS BUSINESS PARK LLC (Proposed) Roosevelt Building (Operating) Wagner Properties Data Center (Approved) Warrenton Group Data Center (Approved) SAMX Data Center (Proposed) Coresite 12100 SV & 12098 SV (Operating, expanding) Infotel Systems Data Center (Operating) Green Energy Center (Approved) ADP Ladysmith Data Hub (Proposed) Carmel Church Data Hub (Approved) Caroline Center for Innovation (Proposed) Thornberry Data Center Campus (Proposed) Gateway Commerce Center (Proposed) SpotsyTech Campus (Approved) AWS Loisdale Station (Under construction) Austin Ridge Logistics Center (Proposed) Globalinx Virginia Beach (Operating, expanding) Telxius Cable Landing Station Virginia Beach (Operating) CyrusOne Vint Hill Data Center (Proposed) DATA CENTER VINT HILL (Operating, expanding) Maple Tree Farm (Proposed, early stage) Vint Hill Corners (Proposed) Imagery: Esri, Maxar
Most of Virginia's data centers are in Northern Virginia: Loudoun County alone has about 50 tracked sites, most of them in Ashburn, followed by Prince William and Fairfax counties. Loudoun supervisors voted 7-1-1 on September 15 to draft a pause of up to 12 months on board votes for new data center and substation applications, and the board is scheduled to vote on it October 20. Farther south, big campuses are under construction in Stafford, Spotsylvania, Louisa and Caroline counties.
Residents have stopped several large projects this year. In Prince William County, developers gave up the court fight over the 1,760-acre Digital Gateway in July, and less than a week later supervisors rejected Dulles Cloud South, which would have been the largest data center project in county history. Hanover County supervisors voted 4-3 in May to deny Tract's 430-acre Mountain Road Technology Park after months of review. In Franklin County, a proposed Crusoe data center at Summit View Business Park near Rocky Mount was dropped in August after residents organized.
On September 18 Gov. Abigail Spanberger signed Executive Order 22, which requires local approval for projects using more than 25 megawatts of power, sets stricter standards for energy, water and noise, and bans secrecy agreements between data centers and state agencies. It is not a moratorium, which some opponents are still calling for. Loudoun's board also takes up changes to its rules for projects already in the pipeline on October 6.
Send a letter to your county commissioners in Virginia Eighty-eight data center projects in Virginia are proposed or under construction right now and three local pauses on new data centers are already in force here. A letter from a resident is a public record they have to answer.
13,864 letters sent so far.
Write my letter Takes about 60 seconds. It goes to every official on the record for your address within 24 hours.
37 counties with tracked projects Only places with at least one project have a page.
Where this comes from The reporting above was written from these. Open one and check it yourself.
Where people here have won Projects stopped by a vote, pulled by their developer, or blocked in court.
Place What happened Date Size
Fredericksburg Penzance
Denied by a vote The city council voted the project down twice over in the early hours of the morning.
Aug 26, 2026
Not reported
Rocky Mount, Franklin County Crusoe
Withdrawn by the developer The data center proposed for Summit View Business Park will not be built.
Aug 17, 2026
150 acres, 100 MW
Prince William County Sanders Lane Assemblage I LLC
Denied by a vote Board of Supervisors voted 8-0 to deny after a five-hour hearing.
Jul 7, 2026
about 1,940 acres, 43 million sq ft
Prince William County QTS / Compass
Withdrawn by the developer Courts voided the approvals (appeal court March 31); Compass withdrew April 29; QTS ended the project July 2.
Jul 2, 2026
about 2,100 acres, 27 million sq ft
Hanover County Tract
Denied by a vote Board of Supervisors voted 4-3 to deny, even after planners recommended approval.
May 27, 2026
about 430 acres, 900 MW
Ashland, Hanover County LS Power
Withdrawn by the developer LS Power pulled its zoning request in a letter from its attorney to the county.
May 1, 2026
205 acres
Hanover County, near Wyndham HHHunt
Withdrawn by the developer Planning Commission voted against it, then HHHunt withdrew.
Jan 28, 2026
about 400 acres, 10 buildings
Louisa County Amazon Web Services
Withdrawn by the developer AWS pulled its permit application after strong resident opposition. AWS later bought nearly 2,000 acres in the county, so it could return.
Jul 23, 2025
7.2 million sq ft
Pittsylvania County Balico LLC
Denied by a vote Board of Supervisors voted 6-1 against the rezoning for a data center campus and a 3,500 MW gas plant, after refusing Balico's third request to delay.
Apr 15, 2025
750 acres, 3,500 MW gas plant
Charles City County Diode Ventures (Roxbury Technology Park)
Withdrawn by the developer Diode dropped the plan after supervisors delayed their vote in the face of local opposition.
2025
515 acres
Catlett, Fauquier County Headwaters Site Development
Withdrawn by the developer Developer withdrew its rezoning days before the planning commission hearing amid resident opposition.
Jul 15, 2024
67 acres, up to 1.4 million sq ft
Ruther Glen, Caroline CountyVALCO
Denied by a vote The board of supervisors voted 5-1 to refuse the comprehensive plan amendment the campus needed, and VALCO withdrew the rezoning.
Jun 18, 2024
855 acres
Story off site ↗
Moratoriums and bans in effect Places in Virginia that have paused or banned new data centers.
Zoning limits on data centers Rules short of a pause: setbacks, noise caps, permit requirements and district limits.