STACK Stafford data center, Stafford, Virginia

Richmond Hwy & Eskimo Hill Rd, Stafford, VA 22554

STACK Infrastructure·Under construction·1,100 MW

The siteImagery: Esri, Maxar

STACK Infrastructure topped out the first building of its Stafford Technology Campus in May 2026, a 500-acre site along Eskimo Hill Road east of Richmond Highway in Stafford County, Virginia. STACK says the campus will eventually hold 1.1 gigawatts of power across four sub-campuses fed by six 300-megawatt substations, with 19 data centers planned in all, calling it the largest project investment in the county's history.

The Stafford County Board of Supervisors voted 6-1 in September 2024 to rezone 504 acres from agricultural to light industrial for a campus of 23 buildings, six electric substations and about 5.5 million square feet; STACK took over the site from Peterson Companies, which had first filed for the rezoning in 2023, in January 2025. The developer agreed to fund $58 million in county capital projects, including water and sewer lines for the center of the county, a connector road between Richmond Highway and Eskimo Hill Road, and land for a fire station.

Supervisor Crystal Vanuch cast the lone vote against the rezoning, saying she was concerned about the project's phasing and about county drinking water being used while a reuse water system, being built by Amazon for its nearby Potomac Church Road facility, was still under construction. "It was never the county's intent to give access to our drinking water to data centers in perpetuity," Vanuch said.

At a League of Women Voters forum in Fredericksburg in September 2026, University of Mary Washington sociology professor Eric Bonds said the campus, now under construction, will be able to draw and distribute 1 gigawatt of power, "enough energy to power 700,000 households, or as much as one nuclear reactor can produce."

The Stafford Technology Campus is one of five approved data center projects in the county, and its 2024 zoning stands, so no further supervisors' vote is required for the campus itself. The local group Protect Stafford is tracking newer data center proposals before the board, working alongside Safeguard Spotsy in neighboring Spotsylvania County.

The facts on file

Company
STACK Infrastructure
Address
Richmond Hwy & Eskimo Hill Rd, Stafford, VA 22554
County
Stafford County, Virginia
Country
United States
Status
Under construction
Power
1,100 MW
On that figure
as reported in source; announced/planned unless status is operating
Operating or planned
2030
Record checked
Sep 16, 2026

Sources

Everything above comes from these. Open one and check it yourself.

Other projects nearby

Sites we track within 40 km.

Share this

XFacebookText message

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.