Home/United States/Arizona/Maricopa County/STACK Phoenix (Avondale)
STACK Phoenix (Avondale) data center, Avondale, Arizona
SE corner of S Litchfield Rd and W Lower Buckeye Rd, Avondale, AZ
STACK Infrastructure·Under construction·225 MW·announced 2020
STACK Infrastructure is building its PHX01 data center campus on 100 acres at Litchfield and Lower Buckeye roads in Avondale, Arizona, in Maricopa County west of Phoenix; the city says the first of three planned buildings, totaling about 1 million square feet, is expected to be completed in 2027. STACK's own listing gives the campus 225 megawatts of power, with closed-loop cooling to cut water use.
STACK announced the project in June 2020 as a 150-megawatt data center on a 79-acre site in the Avondale Techplex, with a 10-year tax waiver and state and local sales tax rebates on data center equipment and labor. "The access to power, fiber, and land provides outstanding opportunity for scale, and the State of Arizona and City of Avondale teams are true partners," said Brian Cox, then STACK's chief executive.
Avondale residents raised water use first, followed by the size and look of the buildings, the city says; Avondale was among the first cities in the region to restrict water-cooled data centers and now allows only closed-loop, air-cooled facilities. Avondale's water utility, like Mesa's and Phoenix's, caps water use for industrial facilities and requires developers to buy supplemental water to go over the cap.
Two more data center campuses are coming to Avondale: Prime Data Centers broke ground in May 2026 at Avondale Boulevard and Lower Buckeye Road, and QTS plans an eight-building campus of about 3.2 million square feet. The city reviews each data center project for utility capacity, traffic, noise and neighborhood fit before it moves forward, and STACK's first building is due to open in 2027.
The facts on file
- Company
- STACK Infrastructure
- Address
- SE corner of S Litchfield Rd and W Lower Buckeye Rd, Avondale, AZ
- County
- Maricopa County, Arizona
- Country
- United States
- Status
- Under construction
- Power
- 225 MW
- Announced
- 2020
- Record checked
- Sep 16, 2026
Sources
Everything above comes from these. Open one and check it yourself.
- avondaleaz.gov/government/departments/economic-development/data-centers-faq/
- www.stackinfra.com/locations/americas/phoenix/phx01/
- www.datacenterdynamics.com/en/news/stack-build-150mw-data-center-phoenix-arizona/
- www.stackinfra.com/about/news-press/press-releases/stack-infrastructure-launches-into-arizona/
- www.aztechcouncil.org/8-metro-phoenix-data-center-developments-to-watch/
- grist.org/technology/arizona-water-data-centers-semiconducters/
Other projects nearby
Sites we track within 40 km.
- Prime Phoenix Campus (Avondale PHX01)5 km
- Stream Goodyear Campus (Phoenix I-V)8 km
- Vantage Phoenix (Goodyear)8 km
- Compass Goodyear (Phoenix)9 km
- Microsoft Goodyear9 km
- Vintage Partners9 km
- Aligned Glendale (75th Ave & Northern)listed on the Maricopa County page12 km
- Microsoft El Mirage13 km
Moratoriums covering this site
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| Maricopa County | Zoning limits | Dec 10, 2025 | No end date | Record off site ↗ |
Share this
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.