Home/United States/Tennessee/Shelby County/xAI Minihard
xAI Minihard data center, Memphis, Tennessee
5420 Tulane Rd, Memphis, TN 38109
xAI·Under construction·announced 2025
Elon Musk said on X on July 29, 2026 that xAI is building a fourth Memphis-area data center, Minihard, next to its Colossus 2 and Macro-harder sites along Tulane Road in Memphis, Shelby County, Tennessee. He said Minihard will hold the same 220,000 GB300 chips as Macro-harder, in a denser configuration, Action News 5 reported. The project is under construction.
The power for the Colossus 2 site that Minihard is joining is under challenge in federal court. In April 2026 the NAACP and its Mississippi State Conference sued xAI and its subsidiary MZX Tech over gas turbines running without an air permit at Southaven, Mississippi, saying the emissions threaten homes, schools and churches in north Mississippi and the Memphis area. "A data center should not be a potential death sentence for a community's health," said Abre' Conner, the NAACP's director of environmental and climate justice.
By May 2026 the turbine count had grown to 33 and the NAACP asked the court for an injunction to halt the pollution; Conner said xAI "showed no remorse by adding six more turbines." In July 2026 xAI said it would remove all 69 temporary turbines at the Southaven site between August 2026 and July 2027 and replace them with a permanent 1.2-gigawatt, 41-turbine power plant.
The facts on file
- Company
- xAI
- Address
- 5420 Tulane Rd, Memphis, TN 38109
- County
- Shelby County, Tennessee
- Country
- United States
- Status
- Under construction
- Announced
- 2025
- Record checked
- Sep 16, 2026
Sources
Everything above comes from these. Open one and check it yourself.
- www.actionnews5.com/2026/07/31/xai-announces-fourth-data-center-turbines-be-removed-southaven-site/
- naacp.org/articles/naacp-sues-xai-illegal-pollution-data-center-power-plant
- earthjustice.org/press/2026/naacp-asks-court-for-emergency-action-to-stop-illegal-air-pollution-from-xais-data
- en.wikipedia.org/wiki/Colossus_(data_center)
Other projects nearby
Sites we track within 40 km.
- xAI Macrohardrr (Colossus 3)under 1 km
- Colossus 2under 1 km
- Colossus 110 km
- Google West Memphis21 km
Share this
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.