Data centers in Wayne County, Michigan: 4 projects mapped
Panattoni's Project Cannoli, a roughly 1-gigawatt data center campus on already industrial-zoned land at I-94 and Haggerty Road in Van Buren Township, got preliminary site plan approval on February 11, 2026, and a substation to serve it got preliminary approval on May 14. Google and DTE Energy announced in March 2026 that Google would be the tenant, with DTE filing the power contracts as a contested case at the Public Service Commission rather than fast-tracking them as it did for the Saline Township project. More than 1,500 people have signed a petition against it.
Township Supervisor Kevin McNamara said the pushback "caused us to really pump the brakes when all of a sudden we had 200 people screaming, 'no data centers, we're all going to die,'" but also called the project potentially "life-changing" for local businesses and schools. In Allen Park, the Planning Commission voted 7-2 in June 2026 to reject Solstice Data's 26-megawatt data center near Melvindale High School, citing an incomplete sound study, and recommended a six-month moratorium.
Detroit has no data center ordinance; its City Council recommended a two-year moratorium that Mayor Mary Sheffield has not adopted, and the City Planning Commission is still drafting rules. Wayne County's other data centers are smaller: Equinix runs a colocation facility in Allen Park, and US Signal is expanding a 2-megawatt data center in Belleville. What comes next: the Public Service Commission's decision on DTE's Google contracts, and Van Buren Township's final approval of Cannoli's site plan.
Data center projects on record in Wayne County
Grouped by the town each site sits in. The report above may name projects that have no record here yet.
Allen Park2
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Solstice Data CenterAllen Park | Solstice | Blocked | 26 MW | |
| Equinix Detroit Center (DT1)Allen Park | Equinix | Not reported | Not reported | Source off site ↗ |
Belleville1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| US Signal Data CenterBelleville | US Signal | 2 MW | Source off site ↗ |
Van Buren Charter Township1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Panattoni Project CannoliVan Buren Charter Township | Panattoni | Approved | 1,000 MW |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Moratoriums and bans in effect
Pauses on new data centers covering this area.
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| Allen ParkTown or city | Moratorium | Jun 9, 2026 | Dec 9, 2026 | Record off site ↗ |
| TaylorTown or city | Moratorium | Jan 20, 2026 | Jan 20, 2027 | Record off site ↗ |
| NorthvilleTown or city | Moratorium | Jan 6, 2026 | Jan 6, 2027 | Record off site ↗ |
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.