Meta·Operating·133 MW

The siteImagery: Esri, Maxar

Meta's data center campus at 1275 North Community Circle in Eagle Mountain, Utah County, Utah, opened in 2018 and now covers more than 500 acres. On September 14, 2026 the company said it would add three more data center buildings, an administration building and a warehouse, on land the city council approved for expansion in October 2025; the council also let Meta buy another 125 acre-feet of water a year, raising its allocation from 500 to 625 acre-feet.

Meta is giving the Lake Mountain School District $600,000 toward land for a new elementary school, about 30 percent of what is needed, plus $1.5 million to the district's education foundation once construction starts and $50,000 a year after that, $10,000 each to two neighboring districts for scholarships, and $450,000 to the Walden Park Observatory. Mayor Jared Gray said: "This is a company that showed up here eight years ago and has kept its commitments to us since."

Separately, Eagle Mountain's city council raised the city property tax rate 183 percent on August 6, 2026, the first increase since 2010, to raise more than $5 million a year, mostly for added Utah County Sheriff's Office deputies. Residents angry about the size of the increase and the tax breaks data centers get organized a referendum; resident Alex Washburn, who led the drive with State Sen. Emily Buss, said: "It's like death by a thousand cuts."

The council then repealed the 183 percent rate and set a new, lower one; residents will still pay about double the old rate. How much water and power the expanded campus will use has not been made public.

The facts on file

Company
Meta
Address
1275 N Community Cir, Eagle Mountain, UT 84005
County
Utah County, Utah
Country
United States
Status
Operating
Power
133 MW
On that figure
Epoch AI estimate of current IT power (80% chance within 1.4x)
Record checked
Sep 16, 2026

Sources

Everything above comes from these. Open one and check it yourself.

Other projects nearby

Sites we track within 40 km.

Share this

XFacebookText message

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.