Data centers in Salt Lake County, Utah: 4 projects mapped
In the year to September 2025, Aligned Data Centers' West Valley site used 80 million gallons of water, while Novva's 1.5 million-square-foot campus in West Jordan used about 3 million, most of it on landscaping, according to records The Salt Lake Tribune obtained. Those are among Salt Lake County's main data centers, alongside Aligned's second site in West Jordan, Oracle's West Jordan facility and DataBank's Bluffdale campus.
The debate here has been less about whether to build than about what the buildings consume, because Utah is one of the driest states and, as Grist and The Salt Lake Tribune reported, how much water a data center uses can vary dramatically.
Read more
Records that The Salt Lake Tribune obtained from municipal water providers for October 2024 to September 2025, published in partnership with Grist, show how much cooling design matters. Novva's chief executive Wes Swenson said its closed-loop system took 55,000 gallons to fill once, and estimated evaporative cooling would need about 250 million gallons a year. Aligned's West Jordan site used 47.4 million gallons, and eBay's South Jordan data center 19.5 million. "Water is extremely cheap," Swenson said. "And cities have generally accommodated that."
The Legislature responded in 2026. HB 76, from Representative Jill Koford, requires new large data centers to report their expected water sources and use to the state before construction and their actual withdrawals every year after they open, with the figures published online. "We live in a desert," Koford said before the session.
HB 507 generally bars local governments from offering incentives to large data centers outside designated regionally significant development zones, and generally caps property tax incentives at 60 percent of the new county revenue a project brings, 80 percent at most. A 2025 law, SB 132, already requires separate accounting for the costs of serving very large loads. According to the Kem C. Gardner Policy Institute, Utah has 48 operating data centers with more than 920 megawatts of capacity, and seven under construction are expected to add about 2,600 megawatts.
Data center projects on record in Salt Lake County
Grouped by the town each site sits in. The report above may name projects that have no record here yet.
West Jordan3
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Aligned Salt Lake City (West Jordan)West Jordan | Aligned Data Centers | Not reported | ||
| Novva West Jordan (Salt Lake City)West Jordan | Novva Data Centers | Not reported | ||
| Oracle West JordanWest Jordan | Oracle | Not reported |
Bluffdale1
| Project | Company | Status | Power | |
|---|---|---|---|---|
| DataBank Salt Lake City metro (SLC1-SLC6)Bluffdale | DataBank | Not reported | Source off site ↗ |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.