Data centers in Tooele County, Utah: 1 project mapped

1 project tracked
·
1 proposed or being built
·
No power figure reported for active projects
Dugway Proving Ground Data Center (Proposed)
Imagery: Esri, Maxar
Tracked project1 site shown

Asked in September 2026 whether a proposed data center in Tooele Valley was dead, Utah Inland Port Authority director Ben Hart said "dead is a very strong word," but "I don't consider it alive right now, that's for sure." The project area is the port authority's 585 acres near Burmester Road and Interstate 80, near the south shore of the Great Salt Lake. Its plan lists data centers among the industries that could get incentives, and the wider project was reported to include a 500-megawatt data center and a truck stop.

Separately, the Army has conditionally picked CyrusOne to build a data center on about 1,200 acres of the Dugway Proving Ground, further south in the county; the Skull Valley Band of Goshute Indians has opposed it over groundwater concerns.

Read more

Emails obtained by the residents' group TooeleCARES show developer Chuck Akerlow of Zenith Development pressing county officials behind the scenes on the Tooele Valley project. In September 2025 he wrote that he had committed to bring a 24-inch high-pressure gas line able to produce 140 megawatts, that he was under nondisclosure agreements with "companies you will recognize," and that he had a letter of intent with a nuclear power company.

In July 2026 he complained that the county's draft data center ordinance discriminated against technology companies, and he floated annexing into Grantsville. Akerlow and a Zenith partner sit on the Interstate Technology Park Public Infrastructure District that could finance infrastructure for the project, and Akerlow has said the project needs port authority financing to work.

Residents organized. At an Aug. 12 hearing the county planning commission heard opposition to a new data center ordinance and to plats for a truck stop and fast-food outlet in the project area, and tabled both, the plats pending a third-party traffic study. In September TooeleCARES delivered a letter signed by more than 1,100 people asking the port authority not to finance the district. "We all live by the same dying (Great Salt) Lake, and our wells are already struggling," resident Amy Lawson told the board.

Hart promised nothing would come to his board without "a very clear green light" from the community: "Tooele Valley (and) Tooele County are signaling they are not OK with it." The county has paused data center applications until its ordinance goes to the planning commission, expected in October, and the County Council, expected in November. Under the state's new HB507, from May 2027 local incentives for large-load data centers will require a state-overseen regionally significant development zone.

Data center projects on record in Tooele County

Grouped by the town each site sits in. The report above may name projects that have no record here yet.

Dugway1
ProjectCompanyStatusPower
Dugway Proving Ground Data CenterDugway CyrusOne Proposed Not reported