Data centers in Dakota County, Minnesota: 4 projects mapped

4 projects tracked
·
3 proposed or being built
·
1 stopped or paused
·
890 MW across all 3 active projects
·
4 moratoriums and bans in effect
Tract Farmington (Approved, 700 MW)Meta Rosemount (Under construction, 178 MW)Oppidan Data Center (Blocked, 300 MW)MSP1 Data Center (Under construction, 12 MW)
Imagery: Esri, Maxar
Tracked projectStopped or pausedBigger dot, more power4 sites shown

Dakota County has Minnesota's first hyperscale data center and four cities with one-year moratoriums against new ones. Meta's 715,000-square-foot building in Rosemount, on the former UMore Park, was nearly complete in July 2026 and due to finish that summer; no report of its opening has been published since. Eagan, Rosemount, Apple Valley and Inver Grove Heights have each paused new data center approvals for a year while they study the effects.

The biggest fight is in Farmington, where the council approved Tract's 12-building Farmington Technology Park in 2024. Two lawsuits followed: the Coalition for Responsible Data Center Development says the city skipped a required environmental review, and Castle Rock Township says the city broke a 2017 annexation agreement. A judge refused to dismiss the township's case on Nov. 13, 2025, and its attorney expected a trial in summer or fall 2026; no result has been published yet. Mayor Joshua Hoyt said the city would "fight it to the extent of the law."

Apple Valley turned down the county's largest proposal: five data center buildings on gravel-mining land, rejected in March 2026 after the city said it lacked the money for the water treatment the project needed. In Inver Grove Heights, the council exempted developer QLevr's 55,000-square-foot project from its moratorium on Sept. 14 after QLevr sued and the city put potential damages at $20 million or more; other proposals there stay paused. In Eagan, a lawsuit is seeking to void that city's moratorium, arguing power use is the state Public Utilities Commission's business, not zoning.

Data center projects on record in Dakota County

Grouped by the town each site sits in. The report above may name projects that have no record here yet.

Apple Valley1
ProjectCompanyStatusPower
Oppidan Data CenterApple Valley Oppidan Blocked 300 MW
Eagan1
ProjectCompanyStatusPower
MSP1 Data CenterEagan Centra Under construction 12 MW
Farmington1
ProjectCompanyStatusPower
Tract FarmingtonFarmington Tract Approved 700 MW
Rosemount1
ProjectCompanyStatusPower
Meta RosemountRosemount Meta Under construction 178 MW

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Moratoriums and bans in effect

Pauses on new data centers covering this area.

PlaceTypeStartedEnds
Apple ValleyTown or city Moratorium Jul 9, 2026 Jul 9, 2027 Record off site ↗
Inver Grove HeightsTown or city Moratorium Jun 26, 2026 Jun 26, 2027 Record off site ↗
RosemountTown or city Moratorium Apr 23, 2026 Apr 23, 2027 Record off site ↗
EaganTown or city Moratorium Feb 17, 2026 Feb 17, 2027 Record off site ↗