Global Data Centers.formerly Florida Data Centers

Home/United States/Minnesota/Hennepin County

Data centers by place

Data centers in Hennepin County, Minnesota: 4 projects mapped

4 projects tracked
·
1 proposed or being built
·
1 operating
·
1 stopped or paused
·
1 with no stage on record
·
No power figure reported for active projects
·
1 moratorium or ban in effect
Legacy Investing Data Center (Star Tribune printing plant) (Withdrawn, 20 MW)Digital Realty Minneapolis (511 11th Ave S) (Not reported)T5 Minneapolis (Operating)US Internet Data Center (Approved)
Imagery: Esri, Maxar
Tracked projectStopped or pausedBigger dot, more power4 sites shown

Minneapolis has spent 2026 deciding whether data centers belong in the city. The City Council passed a six-month moratorium on new data centers citywide on June 25, with one exception for smaller downtown projects, and must decide by Nov. 21, 2026 whether to extend the pause or write permanent rules. Minnetrista, which has had no applications, adopted its own one-year moratorium on Aug. 3.

The downtown exception got its first test when Legacy Investing signed to buy the Star Tribune's shuttered printing plant for a 20-megawatt data center. Hundreds of residents opposed it at neighborhood forums in August over its environmental impact and jobs; in September the company withdrew its application and pulled out of the deal. Council member Aurin Chowdhury, the pause's lead author, said the city lacks "a modern regulatory framework for data centers," while Michael Rainville called it "policy by fear, not facts."

Elsewhere the scale is smaller. Robbinsdale approved a variance for a 4,000-square-foot facility that US Internet's chief financial officer called "really a switching station," not one of "the big behemoths." The county's table also lists Digital Realty and T5 Data Centers sites in Minneapolis, with no stage or size yet reported.

Data center projects on record in Hennepin County

Grouped by the town each site sits in. The report above may name projects that have no record here yet.

Minneapolis3
ProjectCompanyStatusPower
Legacy Investing Data Center (Star Tribune printing plant)Minneapolis Legacy Investing Withdrawn 20 MW
Digital Realty Minneapolis (511 11th Ave S)Minneapolis Digital Realty Not reported Not reported Source off site ↗
T5 MinneapolisMinneapolis T5 Data Centers Operating Not reported Source off site ↗
Robbinsdale1
ProjectCompanyStatusPower
US Internet Data CenterRobbinsdale US Internet Approved Not reported

Where this comes from

The reporting above was written from these. Open one and check it yourself.

Moratoriums and bans in effect

Pauses on new data centers covering this area.

PlaceTypeStartedEnds
MinneapolisTown or city Moratorium May 22, 2026 Nov 21, 2026 Record off site ↗

Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.