Home/United States/Missouri/Jackson County
Data centers in Jackson County, Missouri: 5 projects mapped
The biggest data center in Jackson County is Nebius's campus on nearly 400 acres near Missouri Highway 78 and Little Blue Parkway in eastern Independence. It broke ground in May and will need at least 800 megawatts of power, which a reopened Blue Valley power plant is to supply. Patmos is also planning a data center in a warehouse at 2500 Little Blue Parkway, with construction priced at about $107 million. Neither project is covered by the 180-day pause on new data center applications that Independence adopted on July 6.
The Independence City Council approved a 90% tax break for Nebius over 20 years, worth $6.26 billion, on a 5-2 vote in March. Residents tried to force a public vote on it, but a judge sided with the city. Voters then elected Kevin King mayor with 60% of the vote. On September 1 they recalled council member John Perkins, who had backed the tax break. "Who's going to want to live next to that?" asked Dawn Hahnfeld, who lives nearby.
In Kansas City, the Plan Commission voted 6-0 in August to deny Revitalization Unlimited's 384-foot data center on top of a historic building in the Quality Hill neighborhood. Jackson County has paused data center land use applications for 180 days from June 22 while it writes rules on safety and distance from homes. The county's pause ends December 19 unless it is extended.
Data center projects on record in Jackson County
Grouped by the town each site sits in. The report above may name projects that have no record here yet.
Kansas City3
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Cielo Digital InfrastructureKansas CityExact site not confirmed | Not reported | Proposed | 500 MW | |
| Revitalization Unlimited Data CenterKansas City | Revitalization Unlimited | Blocked | 30 MW | |
| Iron Mountain Kansas City (KCM-1)Kansas City | Iron Mountain Data Centers | 3.9 MW | Source off site ↗ |
Independence2
| Project | Company | Status | Power | |
|---|---|---|---|---|
| Nebius Data CenterIndependence | Nebius | Under construction | 800 MW | |
| Patmos Data CenterIndependence | Patmos | Proposed | 70 MW |
Where this comes from
The reporting above was written from these. Open one and check it yourself.
Moratoriums and bans in effect
Pauses on new data centers covering this area.
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| IndependenceTown or city | Moratorium | Jul 6, 2026 | Jan 2, 2027 | Record off site ↗ |
| Jackson County | Moratorium | Jun 22, 2026 | Dec 19, 2026 | Record off site ↗ |
Zoning limits on data centers
Rules short of a pause: setbacks, noise caps, permit requirements and district limits.
| Place | Type | Started | Ends | |
|---|---|---|---|---|
| Kansas CityTown or city | Zoning limits | Jan 16, 2026 | No end date | Record off site ↗ |
Every project above is drawn from public records, filings and local reporting. Each row links to what it is based on. Statuses change, so check the source date before you rely on one. Found something wrong? Write to [email protected] and it gets fixed.